William Lee, (Arch Tech) Senior Site Manager

536 Prince Edward Drive Etobicoke, ON M8X 2M5

Toronto

Value

Sq. footage

Steelecase Construction – 1year

Allendale Long Term Care Facility, Milton $2.8 Million 50,000 sq ft
Site Superintendent
Retrofit interior of existing facility with new architectural finishes and upgrade mechanical Heat Pumps, BoilersBAS etc.

$2.8 Million

50,000 sq ft

Milton Town Library $3.1 Million 12,000 sq ft
Site Superintendent
Built Concrete Foundation Walls, Piers, Slab on Grade and Underground Services when Construction came to a grinding halt due to Structural Steel Delays.

$3.1 Million

12,000 sq ft

U of T, Hydrogen Laboratory $1.7 Million 1,000 sq ft
Site Superintendent
Retrofit existing classrooms into a new Hydrogen
Research Laboratory

$1.7 Million

1,000 sq ft

Canning Contracting Limited – 2 years

St Leonard’s House
Site Superintendent
Incorporate a 3 storey building addition to an existing Long
Term Homeless/Half Way House Shelter with a commercial
Kitchen, Parking Lot and Landscaping

$3.5 Million

26,303 sq ft

Dalton Engineering & Construction – 5 years

Boulevard Club
Site Superintendent
Transform existing daycare facility into new barrier free
washrooms while transforming existing fitness centre into new
daycare facility and recreation room.

$1.0 Million

8,400 sq ft

Parkway Honda
Site Manager
Incorporate an addition to an existing auto service building.
Retrofit existing service, sales and leasing areas in an
operational facility.

$6.3 Million

33,100 sq ft

Mintz (Accounting) Partnership
Site Manager
Retrofit existing two-story tenant space into a new corporate
office for over 100 staff.

$3.1 Million

18,800 sq ft

Turning Point Youth Shelter
Site Manager
Retrofit 143 year old structure by underpinning the foundation,
installing an elevator and upgrading of the entire mechanical
and electrical systems.

$2.3 Million

16,200 sq ft

Princess Margaret Hospital, Gene Profiling Lab
Site Superintendent
Incorporate research labs (3) and offices within an operating
hospital facility

$3.0 Million

3,500 sq ft

Air Canada Centre –300 Level
Site Superintendent
Construct mezzanine to provide change rooms, uniform
storage, and first-aid station. Retrofit private boxes

$1.3 Million

6,800 sq ft

Princess Margaret Hospital
Site Superintendent
Retrofit interior of an existing facility into Canada’s first
Research Stem Cell Processing Centre (3rd in the world). This
project included Independent Clean Rooms (5) with hepa air
filtration, long term hydrogen storage tanks and support space
(4 office spaces and waste disposal)

$4.0 Million

2,900 sq ft

Alliance Atlantis Film Studios
Site Superintendent
Retrofit multi-tenant administration office space for over 70
staff.

$1.6 Million

23,600 sq ft

Affinium Pharmaceuticals
Site Superintendent
Interior retrofit of existing classrooms into biotechnology type 3
research laboratories and offices

$2.1 Million

18,200 sq ft

Ellis-Don Construction Ltd. 2-1/2 years

Old Navy Distribution Centre (Brampton)
Assistant Project Manager
Co-ordinate scopes of work with drawings, specifications and
budget requirements. Issue Tenders and award Contracts.

$16.0 Million

750,000 sq ft

Princess Margaret Hospital, AMGEN & Breast Elevator
Site Superintendent
Upgrade chilled water system for laboratories. Co-ordinate
subcontractors, and install new elevator in active hospital.

$2.0 Million

Toronto Hospital Redevelopment & Restacking Program,
Princess Margaret Hospital
Assistant Superintendent
Interior retrofit existing facility into clinics, laboratories, offices,
waiting rooms, patient rooms, nurse stations, library etc.

$14.0 Million

86,000 sq ft

Professional Qualifications:

Architectural Technologist, George Brown College, 1995